Surfacing solutions for Europe's busiest exhibition venue
Rio Group has provided Birmingham's
NEC with surfacing solutions for over
twenty years, and was delighted to
help deliver its most recent
improvement: a major project to
remodel the main entrance areas.
Further work is now underway, on the east
side of the building adjacent to the Concert
Hall and Crowne Plaza Hotel, together with
the main road to the Metropole Hotel, to
plane off worn surfacing in 9,000 square
metres of road, before replacing with
machine laid 10mm stone mastic asphalt.
3,000 square metres of car park surfacing
will also be replaced at the same time.
On completion all road markings will be
replaced and reinstated as required.
Rio Group is responsible for ensuring the
continued flow of traffic and easy access
through all affected areas, allowing business
as usual at Europe's busiest exhibition venue.
|